Mozambique has approved an expansion of ExxonMobil’s $26 billion Rovuma liquefied natural gas (LNG) project, increasing planned liquefaction capacity from 15.2 million to 18.6 million tonnes a year and clearing a key regulatory hurdle for one of Africa’s largest proposed gas developments.
The revised development plan was approved by the Council of Ministers and forms part of efforts to advance the project toward a final investment decision.
The Instituto Nacional de Petróleo said the updated design will use electrically powered gas-processing modules, a move expected to improve efficiency, reduce construction costs and cut emissions by about 40 percent compared with the original plan approved in 2019.
The Rovuma LNG project is designed to process natural gas from offshore Area 4 in the Rovuma Basin through an onshore liquefied natural gas complex in northern Mozambique.
The revised plan envisages 12 modular liquefaction units, with first production previously targeted for 2031.
Mozambique expects the development to deliver significant economic benefits.
Authorities estimate local companies could secure about $6 billion in supply and service contracts while 25 percent of gas production has been earmarked for the domestic market.
The government has projected state revenues of up to $121 billion over a 25-year period.
The approval follows the selection in August of a consortium led by Saipem for preliminary engineering and procurement work.
The group, which also includes McDermott, Daewoo Engineering & Construction and China Petroleum Engineering & Construction Corporation, has received a letter of intent, although a full engineering, procurement and construction contract remains contingent on a final investment decision.