Uganda has once again postponed the launch of its first commercial crude oil production and export, due to, according to its officials, international supply chain bottlenecks and disruptions linked to the war in Iran.
Officials from the Uganda National Oil Company (UNOC) and the Petroleum Authority of Uganda (PAU) on Tuesday announced that Uganda’s first oil production and exports have now been pushed until the end of June 2027.
According to the PAU, the Middle East conflict delayed key equipment and material deliveries such as parts for metering, electrical instrumentation and telecommunications systems required to finalize the production and evacuation infrastructure.
Experts from PAU said while construction work at the $5.6-billion East African Crude Oil Pipeline (EACOP) is more than 90 percent complete, critical supporting facilities such as pump stations three and four and the pipeline’s electrical, instrumentation, telecommunications and security systems are still incomplete, requiring coordinated testing and commissioning across the EACOP, Tilenga, Kingfisher and Tanga projects.
Uganda is projected to achieve a combined peak output of about 230,000 barrels of oil per day across TotalEnergies’ (NYSE:TTE) Tilenga project and CNOOC’s Kingfisher project.
Production is expected to kick off with an initial stage of around 25,000 barrels per day from the Kingfisher field, rising to the field’s 40,000-barrel-per-day capacity, while Tilenga ramps up toward its 190,000-barrel-per-day peak.
According to the Petroleum Authority of Uganda, the government will potentially earn between 1.5 and 2.5 billion dollars per year once oil production begins.
The oil export delay has muddied Uganda’s financial outlook considerably, with S&P Global Ratings revising the outlook on the country’s B- sovereign credit rating from positive to stable.